Pond restoration Birtley Estate
The Birtley Estate applied for ยฃ11,525.28 to restore two woodland ponds which had become heavily silted up over the years. The project also included the repair of the dam between the two ponds and the construction of a wooden dipping platform to enable the educational groups that use the woodland to have safe access to the pond.
Project summary
| Total grant awarded | ยฃ11,525.28 |
| Total cost of project: | ยฃ11,525.28 |
| Project start date: | 23/10/2023 |
| Project end date: | 30/01/2024 |
| Location | Bramley |